2022 Road Improvement Program

 Asphalt Specialists, Inc. (ASI) of Pontiac, Michigan, has begun work on Phase 2 of the Village’s 2022 Road Improvement Program.

Phase 2, which began Monday, June 20 and will end on Friday, July 1, includes the parking lot at Clara Miller Park, Brushwood Drive, Dunreath Street, Pinecrest Drive, Wakito Street, West Drive (north of Dunreath Street), Winghamton Avenue and Wolverine Drive (from S. Commerce Road to Lucille Drive).

The parking lot at Clara Miller Park is closed until Saturday, June 25 for repaving and striping.  Clara Miller Park is open while the lot is being repaved.
Park users are encouraged to park on the west side of Brisbane Street, near the Lakes Community Trail.

Please contact the Village Hall at (248) 624-1710 if you have any questions.

Tentative Phase 2 Paving Schedule
Printable Paving Notice